Have the students and staff adjusted well to the active construction at the high school?

It has not effected anything going on in the classrooms. We have been observing the class rooms since school has started and have not seen a difference.

What is the status of phase I of the new high school?

We are currently done with 90 percent of phase one and expect construction to be completed by early December.

Once completed how long until classes can be held in the new building?

Classes will not be held in the building until mid-February. We need to complete the construction of the canopy leading from the parking lot to the new high school entrance before we can safely let students enter the building.